Power outage to 88,000 customers 'entirely avoidable'

The fallen pylon after too many nuts were removed at the same time. Photo: Transpower
The fallen pylon after too many nuts were removed at the same time. Photo: Transpower
A massive power outage across most of Northland was entirely avoidable, a major report into the cause has found.

The Electricity Authority this morning released its review into the collapse of the electricity transmission tower that left 88,000 households and businesses in Northland without power for at least 12 hours.

On June 20 this year, a relatively inexperienced and inadequately supervised worker removed nuts from three of the four legs of the pylon, causing it to collapse.

The report found Transpower missed an opportunity to take action when staff raised concerns relating to baseplate refurbishment of the tower in 2021.

A senior engineer had then identified a gap in the knowledge of maintenance crews undertaking the foundation work and recommended Transpower organised new training sessions with all new crew members, and to do refresher training every 12 months.

"This wasn't acted on. The failure to respond to, or action, the concerns raised does not align with the principles of proactive risk management and continuous improvement that we would expect to see within Transpower," the report said.

"Although Transpower described the event as 'unprecedented and inconceivable', the underlying factors that contributed to the tower's collapse were entirely avoidable," the report found.

Energy minister Simeon Brown said Transpower's failure to act on these opportunities had led to terrible consequences for the people of Northland, and there was evidence that the removal of all nuts from more than one tower leg was not a one-off event.

"These are incredibly concerning findings, and the report identifies a number of recommendations that I expect Transpower will fully accept and act with urgency to address," he said.

The report estimates the economic loss for Northland ranged between $37.5 million to $80 million.

Brown presented the findings today, which come with 26 recommendations for Transpower, including improving its training for contractors.

"I will be writing to the Electricity Authority to express my expectation that the recommendations are implemented and that they work with Transpower on the implementation of the recommendations that are relevant to them."

In August, an independent report found contractor error was to blame for the collapse of the power pylon in Golrit in the Auckland region.

It said the inexperienced and inadequately supervised worker removed nuts from three of the four legs of the pylon, compromising its stability and causing it to rupture and fall, cutting power. 

At the time of the outage, Brown ordered the Electricity Authority to review the cause.